Filter by category
Filter by Date
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 16/01/2026
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 132790 has been updated to the following:
[1.] From 1500 hrs 16/01/2026 to 1530 hrs 16/01/2026.
The forecast capacity reserve requirement is 770 MW.
The minimum capacity reserve available is 593 MW.
[2.] From 1600 hrs 16/01/2026 to 2030 hrs 16/01/2026.
The forecast capacity reserve requirement is 775 MW.
The minimum capacity reserve available is 565 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 16/01/2026
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1530 hrs to 1800 hrs 16/01/2026.
The forecast capacity reserve requirement is 779 MW.
The minimum capacity reserve available is 707 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/01/2026
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 132516 is cancelled at 0030 hrs 06/01/2026.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/01/2026
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1700 hrs 08/01/2026 to 1830 hrs 08/01/2026.
The forecast capacity reserve requirement is 1207 MW.
The minimum capacity reserve available is 1112 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 07/01/2026
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 132494 is cancelled at 0820 hrs 05/01/2026.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 07/01/2026
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 132489 has been updated to the following:
[1.] From 1730 hrs 07/01/2026 to 2100 hrs 07/01/2026.
The forecast capacity reserve requirement is 373 MW.
The minimum capacity reserve available is 294 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 07/01/2026
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1730 hrs 07/01/2026 to 1800 hrs 07/01/2026.
The forecast capacity reserve requirement is 349 MW.
The minimum capacity reserve available is 325 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 23/12/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 132000 is cancelled at 0800 hrs 22/12/2025.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 23/12/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1500 hrs 23/12/2025 to 1530 hrs 23/12/2025.
The forecast capacity reserve requirement is 821 MW.
The minimum capacity reserve available is 724 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations