AusNet Services OSR - Secure supply and enable connections: Wollert

31/03/2026
Market Network Service Provider
StageOptions Screening Report
ConvenorAEMO NSP
Initiated31/03/2026
Accepting submissions?Yes
Submissions close23/06/2026

Options Screening Report – Summary

Regulatory Investment Test – Distribution – March 2026

AusNet is initiating this Regulatory Investment Test for Distribution (RIT-D) to investigate and evaluate options to efficiently maintain a reliable supply of power to the customers in the Wollert /Epping area as the forecast demand exceeds the capacity of several 22kV distribution feeders originating from Epping Zone Substation (EPG ZSS), that currently supplies the load in the growth area.

Publication of this Options Screening Report (OSR) represents the first step in the RIT-D process in accordance with clause 5.17 of the National Electricity Rules (NER) and section 4.2 of the RIT-D Application Guidelines.

The purpose of the RIT-D is to identify the credible option that maximises the present value of net economic benefit to all those who produce, consume and transport electricity in the National Electricity Market (NEM).

AusNet welcomes written submissions on the credible options presented in this OSR and invites proposals from proponents of potential non-network options. Submissions should be emailed to [email protected] on or before 23 June 2026. In the subject field, please reference ‘RIT-D OSR Wollert.’