Consultation on Automation of Negative Residue Management for the implementation of transmission loops

19/11/2025
Market National Electricity Market
StageFinal Report
ConvenorAEMO NEM
Initiated13/06/2025
Accepting submissions?No

Timeline

  • Consultation paper published
    13 June 2025
  • Submissions due on consultation paper
    11 July 2025
  • Draft report and related documents published
    17 September 2025
  • Submissions due on draft report and related documents
    18 October 2025
  • Final report and related documents published
    19 November 2025

Key contact

A mail icon. Email: [email protected]

Matters under consultation

This consultation paper commences the first stage of the standard rules consultation process conducted by AEMO to amend the Automation of Negative Residue Management document to include a process that is appropriate for transmission loops (proposal) in preparation for the inclusion of the Project EnergyConnect (PEC) interconnector in AEMO’s dispatch processes. Negative residue management (NRM) is the process used by AEMO to manage negative settlements residue and is applied under National Electricity Rules (NER) 3.8.1(b)(11).

At this stage PEC is due to be completed by October 2026, with inter-network testing due to commence in late 2026. From early next year AEMO will begin work towards implementation of PEC as a transmission loop in dispatch processes, in preparation for October 2026.

The current AEMC rule change Inter-regional settlement residue arrangements for transmission loops is focused on allocation of negative settlement residues. The AEMC confirmed in their Draft Determination their intention to support AEMO’s approach to clamping in transmission loops where counter-price flows would only be clamped if the net inter-regional settlement residues (IRSR) for the loop is negative. Therefore, this consultation is focused on the process of managing these negative IRSR around the loop. Note that the threshold for NRM (currently set at -$100,000) does not form part of the scope of this consultation. 

In summary, AEMO is consulting on the following elements:

  • The treatment of transmission loops, as arises from the implementation of the PEC interconnector.
  • ‘Cycling’ issue in the existing clamping process.
  • Other possible enhancements or changes to the existing NRM process and design.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm