Powercor has published the Project Assessment Conclusions Report (PACR) for Altona Terminal Station West (ATS-WEST). Publication of this PACR represents the last step in the Regulatory Test for Transmission (RIT-T) process.
There is currently insufficient import capacity to supply the forecast maximum demand at ATS-WEST if a forced outage of a transformer occurs and electrical demand growth in the western growth corridor area is expected to cause exceedance of station capacity by 2033.