PACR: Emerging Load Constraint - Deer Park Terminal Station DPTS

02/02/2026
Market Network Service Provider
StageProject Assessment Conclusions Report
ConvenorAEMO NSP
Initiated02/02/2026
Accepting submissions?No

Powercor has published the Project Assessment Conclusions Report (PACR) for Deer Park Terminal Station (DPTS). Publication of this PACR represents the last step in the Regulatory Test for Transmission (RIT-T) process.

There is currently insufficient import capacity to supply the forecast maximum demand at DPTS if a forced outage of a transformer occurs and electrical demand growth in the western growth corridor area is expected to cause exceedance of station capacity by 2029.