Settlements package 4: Transmission Network Service Provider Negative Settlements Residue
Overview: This procedure outlines the process to enable AEMO to recover amounts arising from negative inter-regional and intra-regional settlements residues in a timeframe that minimises the impact on the settlement of Market Participants.
Status: Final Determination Published
Consultation approach: Due to the administrative nature of the proposed changes, this consultation involved a single round of consultation.
| Key dates | |
| Publish notice for consultation and draft procedure | 01/04/2019 |
| Submissions due | 03/05/2019 |
| Publish final procedure and final determination | 14/05/2019 |
| High Level Impact Assessment |
| HLIA – TNSP Negative Settlements Residue Procedure |