STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/05/2026
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 0000 hrs 19/05/2026 to 2330 hrs 19/05/2026.
The forecast capacity reserve requirement is 1190 MW.
The minimum capacity reserve available is 755 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/05/2026
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1300 hrs 18/05/2026 to 0000 hrs 19/05/2026.
The forecast capacity reserve requirement is 1185 MW.
The minimum capacity reserve available is 1120 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 15 May 2026
NON-CONFORMANCE VIC1 Region Friday, 15 May 2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA2
Duration: 15/05/2026 20:30 to 15/05/2026 20:35
Amount: -16 MW
Constraint: NC-V_LYA2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 15/05/2026
Cancellation - AEMO Intervention Event - SA region 15/05/2026
Refer to Market Notice 144086
The AEMO Intervention Event and all associated directions are cancelled from 1635 hrs on 15/05/2026.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS
Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS
Refer to Market Notice 144087
Direction is cancelled from: 1635 hrs 15/05/2026
Manager NEM Real Time Operations
Direction - in SA region to AGL SA Generation Pty Limited - Barker Inlet Power Station
Direction - in SA region to AGL SA Generation Pty Limited - Barker Inlet Power Station
Refer to Market Notice 144086.
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - Barker Inlet Power Station at 1555 hrs 15/05/2026
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 1555 hrs 15/05/2026
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state.
Expected duration: Until further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 15/05/2026
Direction - SA region 15/05/2026
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1600 hrs on 15/05/2026.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink - NSW region - 15/05/2026
Inter-regional transfer limit variation - Directlink No. 2 Leg - NSW region - 15/05/2026
A planned outage of Directlink No. 2 Leg in the NSW region was scheduled from 0700 hrs 11/05/2026 to 1600 hrs 18/05/2026.
The outage has been completed and Directlink No. 2 Leg returned to service at 1410 hrs 15/05/2026
Constraint set(s) revoked: N-MBTE_1
Manager NEM Real Time Operations
Initial - CHG0110694 - Renewal and update of AEMO's FRC RELAY and GAS server certificate.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Business to Business data exchange
Change Title: Renewal and update of AEMO's FRC RELAY and GAS server certificate.
Change Start Date & Time: 15/06/2026 09:00:00
Change End Date & Time: 15/06/2026 17:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: AEMO's FRC Gas Hub web services need to have their server certificates updated every 3 years with new certificates to replace expiring ones.
Participants connecting to these endpoints or receiving requests from AEMO's FRC Gas Hub platforms and have authorisation mechanisms like certificate fingerprinting in place will notice a change in AEMO's server's certificate fingerprint and will need to update their systems accordingly.
The certificate relates to the FRC HUB RELAY, participants WILL need to update the profile that communicates with the FRC HUB RELAY with the new root(AEMO-RCA G2)/intermediate(AEMO-ICA-TEST G1) and FRC-HUB-RELAY-Prod certificates.
This will need to be done to avoid the inability to send messages to the relay.
The certificates can be downloaded from the link below:
https://www.digicert.com/secure/download-certificate/jtw2pmbnyfp2411c6rztc3h9x65fqqw
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.