Market Notices

130347RESERVE NOTICE02/11/2025 12:58:45 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/11/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1600 hrs 03/11/2025 to 1800 hrs 03/11/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1109 MW.


Manager NEM Real Time Operations
130346RECLASSIFY CONTINGENCY01/11/2025 11:16:23 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - QLD region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 130338 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 2315 hrs 01/11/2025.

Manager NEM Real Time Operations
130345RECLASSIFY CONTINGENCY01/11/2025 11:16:21 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - QLD region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 130337 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 2310 hrs 01/11/2025.

Manager NEM Real Time Operations
130344RECLASSIFY CONTINGENCY01/11/2025 10:52:57 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - NSW region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 130339 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 2250 hrs 01/11/2025.

Manager NEM Real Time Operations
130343RESERVE NOTICE01/11/2025 10:20:51 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 03/11/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 130341 is cancelled at 2215 hrs 01/11/2025.

Manager NEM Real Time Operations
130342RECLASSIFY CONTINGENCY01/11/2025 09:29:30 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 01/11/2025 21:29

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 130340

Auto-generated on behalf of Manager NEM Real Time Operations
130341RESERVE NOTICE01/11/2025 08:35:48 PM

STPASA- Forecast Lack Of Reserve Level 2 (LOR2) in the {NSWRegion on 03/11/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1830 hrs 03/11/2025 to 1900 hrs 03/11/2025.
The forecast capacity reserve requirement is 1209 MW.
The minimum capacity reserve available is 1193 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
130340RECLASSIFY CONTINGENCY01/11/2025 08:24:10 PM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 01/11/2025 20:24 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
130339RECLASSIFY CONTINGENCY01/11/2025 05:18:45 PM

Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - NSW region.

AEMO ELECTRICITY MARKET NOTICE.

Refer AEMO Market Notice 130328

AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible in the Northern Rivers, Northern Tablelands and parts of Mid North Coast, Hunter, North West Slopes and Plains, Central Tablelands and Central West Slopes and Plains Forecast Districts because of the existence of widespread abnormal conditions namely severe weather in the NSW region.

AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).